| Total number of EVAs: 161 times | Total EVA duration: 1015H37M | ||||
| Number | Mission | EVA Date | EVA Duration | Spacesuit | Remarks |
|---|---|---|---|---|---|
| 161 | Expedition 28 Crew |
2011.8.3 - 4 | 6H23M | Orlan | · Deployed a nanosatellite(ARISSat-1) · Installation of external onboard laser communications terminal outside the Zvezda module · Retrieval of antenna outside the Zvezda module · Installation of Biorisk experiment outside the Pirs module |
| 160 | STS-135 (ULF7) |
2011.7.12 - 13 | 6H31M | EMU | · Packed a PM (Pump Module) failed in 2010 into the shuttle's cargo bay · Installed the Robotic Refueling Mission(RRM) experiment on a platform on Dextre · Installed materials experiment on a Express Logistics Carrier 2(ESP-2) · Installed an insulating cover on the end of the Pressurized Mating Adaptor 3(PMA-3) |
| 159 | STS-134 (ULF6) |
2011.5.26 - 27 | 7H24M | EMU | · Stow the Orbiter Boom Sensor System on the S1 truss · Outfit the OBSS |
| 158 | 2011.5.25 | 6H54M | EMU | · Installed a power and data grapple fixture on Zarya · Installed a video signal converter on Zarya · Ran power cables from the U.S. segment to Zarya |
|
| 157 | 2011.5.22 | 8H07M | EMU | · Refill one of the station’s cooling loops with ammonia · Lubricate the Solar Alpha Rotary Joint (SARJ) on the port truss · Installing a camera cover on Dextre · Lubricate the Latching End Effector (LEE) of the Dextre |
|
| 156 | 2011.5.20 | 6H19M | EMU | · Retrieve the Materials International Space Station Experiments 7 (MISSE-7) · Installed the MISSE-8 · Installed a light on the S3 truss · Installed a jumper cable on the Photovoltaic Thermal Control System (PVTCS) · Installed antennas for the External Wireless Communication System |
|
| 155 | STS-133 (ULF5) |
2011.3.2 | 6H14M | EMU | · Retrieve a lightweight adapter plate assembly · Vent the remaining coolant from the pump · Remove insulation from the Express Logistics Carrier 4 · Installing a camera light pan and tilt assembly on the Dextre, and removing some insulation from Dextre |
| 154 | 2011.2.28 | 6H34M | EMU | · Install the extension cable between the Unity and Tranquility nodes · Move a failed pump module · Install vent tool on the pump module · Install a camera wedge · Extende the rail track · JAXA Education Payload Observation “Message in a Bottle” |
|
| 153 | Expedition 26 Crew |
2011.2.16 | 4H51M | Orlan | · Installation of two scientific experiments outside the Zvezda module · Retrieval of two exposed experiment panels from the exterior of the Zarya module · Removal and jettison of a space suit foot restraint |
| 152 | 2011.1.21 | 5H23M | Orlan | · Install of a new high-speed data transmission system · Remove an old plasma pulse experiment · Install a camera for the Russian Mini-Research Module-1 (MRM1) · Retrieve a materials exposure package |
|
| 151 | Expedition 25 Crew |
2010.11.15 | 6H27M | Orlan | · Install the URM-D portable multipurpose workstation on Plane IV (starboard side) of the SM Work Compartment (RO) Large Diameter (LD) · Install a gap spanner on Docking Compartment-1 (DC-1) · Install struts between MRM-2 & the SM and MRM-2 & the FGB · Conduct the “Test Eexperiment on the SM and DC-1, which involved taking samples from the external surfaces of the modules |
| 150 | Expedition 24 Crew |
2010.8.16 | 7H20M | EMU | · Install the spare PM (Pump Module) to S1 truss · Mate and open associated fluid QDs (Quick Disconnect) on the spare PM · Mate electrical and data cables to the spare PM |
| 149 | 2010.8.11 | 7H26M | EMU | · Close and demate remaining QDs on the failed PM · Remove failed PM from S1 truss and stowed it on the MT (Mobile Transporter) · Prepare the spare PM |
|
| 148 | 2010.8.7 | 8H03M | EMU | · Close and demate part of QDs on the failed PM | |
| 147 | 2010.7.26 | 6H42M | Orlan | · Remove and replace Zvezda ATV video camera · Route and mate MRM1 Command & Data Handling/Ethernet cables to Zvezda & Zarya · Route and mate MRM1 Kurs-P cables to Zarya |
|
| 146 | STS-132 (ULF4) |
2010.5.21 | 6H46M | EMU | · Replace P6 batteries · Install a backup ammonia coolant jumper between the Port 4 and Port 5 truss · Remove the PDGF (Power and Data Grapple Fixture) |
| 145 | 2010.5.19 | 7H09M | EMU | · Remove a cable snag in the orbiter boom sensor system’s pan · Replace P6 batteries · Tighten bolts holding spare space-to-ground antenna's dish to its boom |
|
| 144 | 2010.5.17 | 7H25M | EMU | · Install spare space-to-ground antenna · Install spare parts platform on the Special Purpose Dexterous Manipulator (Dextre) · Loosen P6 battery bolts |
|
| 143 | STS-131 (19A) |
2010.4.13 | 6H24M | EMU | · Connected fluid lines to the new S1 ATA (Ammonia Tank Assembly) · Retrieved A/L (Airlock) MMOD (Micrometeoroid/Orbital Debris) shields from ESP-2 (External Stowage Platform) 2, transferring them to the A/L for return · Stowed the old ATA on the LMC (Lightweight Multipurpose Experiment Support Structure Carrier) in the Shuttle payload bay · Relocated a portable foot restraint and prepared cables on the Zenith 1 truss |
| 142 | 2010.4.11 | 7H26M | EMU | · Retrieval old ATA (Ammonia Tank Assembly) · Installation of new ATA |
|
| 141 | 2010.4.9 | 6H27M | EMU | · Prepared a new ammonia tank · Retrieved an experiment from the Japanese Kibo Laboratory exposed facility · Replaced a Rate Gyro Assembly on one of the truss segments |
|
| 140 | STS-130 (20A) |
2010.2.16 | 5H48M | EMU | · Connect pressurized mating adapter 3 (PMA-3) heater and data cables · Open ammonia flow to Tranquility · Disconnect temporary Tranquility heating cables · Remove Cupola insulation covers · Release Cupola window covers launch locks · Install Tranquility handrails, worksite interfaces and gap spanners |
| 139 | 2010.2.13 | 5H54M | EMU | · Connect the Tranquility to the ETCS (External Thermal Control System) · Outfit the Tranquility · Preparation for the relocation of Cupola |
|
| 138 | 2010.2.11 | 6H32M | EMU | · Install the new Tranquility node on the Unity node · Move temporary storage platform from the special purpose dexterous manipulator to the P5/P6 truss segment · Preparation for the relocation of Cupola |
|
| 136 | STS-129 (ULF3) |
2009.11.23 | 5H42M | EMU | · Transfer high pressure gas tank · Install Materials International Space Station Experiment 7 |
| 135 | 2009.11.21 | 6H08M | EMU | · Install Grappling Adaptor To On-Orbit Railing (GATOR) assembly · Relocate floating potential measurement unit · Set up S3 payload attachment system · Install wireless video system external transceiver assembly |
|
| 134 | 2009.11.19 | 6H37M | EMU | · Install spare S-band antenna structural assembly · Install redundant space-to-ground antenna cabling · Remove Unity node handrail and replace with ammonia line routing bracket · Lubricate Payload Orbital Replacement Unit Accommodation and Japanese robotic arm · Reposition local area network cable on Zarya · Troubleshoot S0 panel · Set up S3 payload attachment system |
|
| 133 | STS-128 (17A) |
2009.9.5 | 7H01M | EMU | · deployment Payload Attachment System (PAS) on the S3 truss. · replacement of Rate Gyro Assembly (RBA) · preparation for the arrival of the Node 3 "Tranquility" /> · replacement of remote power control module · replacement of GPS antenna |
| 132 | 2009.9.3 | 6H39M | EMU | · installation of new ATA (Ammonia Tank Assembly) · retrieval old ATA · installation of protective lens covers on the cameras of the station’s robotic arm |
|
| 131 | 2009.9.1 | 6H35M | EMU | · removal of ATA (Ammonia Tank Assembly) · retrieval EuTEF (European Technology Exposure Facility) · retrieval MISSE-6 (Material ISS Experiment-6) |
|
| 130 | STS-127 (2J/A) |
2009.7.27 | 4H54M | EMU | · installation of VE (Visual Equipment) · adjustment of multi-layer insulation around the Dextre · split out power channels for two space station Control Moment Gyroscopes · installation of handrails on the Kibo Japanese Experiment Module - Pressurized Module (PM) |
| 129 | 2009.7.24 | 7H12M | EMU | · replacement of P6 Batteries | |
| 128 | 2009.7.22 | 5H59M | EMU | · preparation for transferring the payloads to the Kibo EF · replacement of P6 Batteries |
|
| 127 | 2009.7.20 | 6H53M | EMU | · transfer spare equipment for the station on External Stowage Platform 3 (ESP-3) | |
| 126 | 2009.7.18 | 5H32M | EMU |
· Kibo/exposed facility berthing mechanism
preparation · Japanese Experiment Module Remote Manipulator System (JEMRMS) maintenance ·deployment Unpressurized Cargo Carrier Assembly Attachment System (UCCAS) of the P3 truss ·release of a window's cover of harmony ·release of a window's cover of unity · CETA (Crew and Equipment Translation Aid) cart modification |
|
| 125 | Expedition 20 Crew |
2009.6.10 | 12M | Orlan | · preparation for the arrival of the Russian Mini-Research Module-2 (MRM2) (replacement of the Zvezda hatch) *Internal Spacewalk |
| 124 | 2009.6.5 | 4H54M | Orlan | · preparation for the arrival of the Russian MRM2 (installed docking antennas) | |
| 123 | STS-119 (15A) |
2009.3.23 | 6H27M | EMU | · relocation of CETA (Crew and Equipment Translation Aid) carts · lubricating the Latching End Effector (LEE) of the SSRMS (Space Station Remote Manipulator System) |
| 122 | 2009.3.21 | 6H30M | EMU | · preparation for replacement of P6 Batteries · installation of a GPS antenna on the Kibo Experiment Logistics Module - Pressurized Section (ELM-PS) · performimg infrared photo/video imagery on S1/P1 radiators |
|
| 121 | 2009.3.19 | 6H07M | EMU | · installation of s6 truss · preparation for deployment of SAW (Solar Array Wing) · removal of the Multi Layered Insulation (MLI) cover |
|
| 120 | Expedition 18 Crew |
2009.3.10 | 4H49M | Orlan | · removal of the straps on the Pirs airlock and docking compartment · inspection & taking photos of Progress antenna · installation of the Expose-R experiment · closing the Multi Layer Insulations (MLI) flap on the SM · re-installation of SKK #9 removable cassette container in nominal position · inspection & taking photos of the exterior of the Russian portion of the station · taking photos of the hardware and routed cables |
| 119 | 2008.12.22 | 5H38M | Orlan | · installation of a Langmuir probe · removal of the Biorisk experiment · installation of the Expose-R experiment and the Impulse experiment |
|
| 118 | STS-126 (ULF2) |
2008.11.24 | 6H07M | EMU | · operations related to the Solar Alpha Rotary Joint (SARJ) · operations related to the Kibo Exposed Facility Berthing Mechanism (EFBM) · installation of a External TV Camera Group (ETVCG) on the Port 1 truss · installation of a GPS antenna on the Kibo Experiment Logistics Module - Pressurized Section (ELM-PS) |
| 117 | 2008.11.22 | 6H57M | EMU | · operations related to the starboard Solar Alpha Rotary Joint (SARJ) | |
| 116 | 2008.11.20 | 6H45M | EMU | · relocation of CETA (Crew and Equipment Translation Aid) carts · lubricating the Latching End Effector (LEE) of the SSRMS (Space Station Remote Manipulator System) · operations related to the starboard SARJ (Solar Alpha Rotary Joint) |
|
| 115 | 2008.11.18 | 6H52M | EMU | · transfer an empty Nitrogen Tank Assembly (NTA)
from External Stowage Platform (ESP-3) to the
shuttle’s cargo bay · installation of a new Flex Hose Rotary Coupler (FHRC) on ESP-3 · removal of the Multi Layered Insulation (MLI) cover on the Kibo Exposed Facility Berthing Mechanism (EFBM) · operations related to the starboard SARJ (Solar Alpha Rotary Joint) |
|
| 114 | Expedition 17 Crew |
2008.7.15 | 5H54M | Orlan | · outfitted the Russian segment's exterior · installation of the VSPLESK science payload (for studying cosmic radiation bursts) · removed the Biorisk experiment container from the Pirs |
| 113 | 2008.7.10 | 6H18M | Orlan | · inspected the Soyuz TMA-12 (removed one pyrobolt, etc.) | |
| 112 | STS-124 (1J) | 2008.6.8 | 6H33M | EMU | · outfitted the Kibo Japanese Experiment Module · replacement of the Nitrogen Tank Assembly (NTA) of S1 truss |
| 111 | 2008.6.5 | 7H11M | EMU | · outfitted the Kibo Japanese Experiment Module · preparation for replacement of the Nitrogen Tank Assembly (NTA) of S1 truss · retrieved a failed external television camera of P1 truss |
|
| 110 | 2008.6.3 | 6H48M | EMU | · release of the Shuttle Remote Manipulator System (SRMS)'s elbow camera strap · assistance with the transfer of the Orbiter Boom Sensor System (OBSS) from S1 truss to the shuttle · preparation for installation of the Kibo Japanese Experiment Module - Pressurized Module (PM) · release of a window's cover of PM · operations related to the starboard Solar Alpha Rotary Joint (SARJ) |
|
| 109 | STS-123 (1J/A) | 2008.3.22 | 6H02M | EMU | · stored the Orbiter Boom Sensor System (OBSS) on S1 truss · inspection of the starboard Solar Alpha Rotary Joint (SARJ) · installation of the Materials ISS Experiment-6 (MISSE-6) on the Columbus · installation of trunnion covers on the the Kibo Experiment Logistics Module - Pressurized Section (ELM-PS) |
| 108 | 2008.3.20 | 6H24M | EMU | · demonstration of the Tile Repair Ablator Dispenser (T-RAD) · replacement of Remote Power Controller Module (RPCM) · remove some of the launch locks from the Harmony |
|
| 107 | 2008.3.17 | 6H53M | EMU | · assemble Dextre · installation of spare equipment for the station on External Stowage Platform 2 (ESP-2) |
|
| 106 | 2008.3.15 | 7H08M | EMU | · assemble Dextre | |
| 105 | 2008.3.13 | 7H01M | EMU | ·preparation for installation of the Kibo Experiment Logistics Module - Pressurized Section (ELM-PS) · assemble Dextre |
|
| 104 | STS-122 (1E) | 2008.2.15 | 7H25M | EMU | · installation of external experiment facilities to the Columbus · retrieval failed Control Moment Gyroscope (CMG) |
| 103 | 2008.2.13 | 6H45M | EMU | · replacement of the Nitrogen Tank Assembly (NTA) · installation of the Multi Layer Insulations (MLI) on the Columbus' trunnion pins |
|
| 102 | 2008.2.11 | 7H58M | EMU | · preparation for installation of the Columbus · preparation for replacement of Nitrogen Tank Assembly (NTA) |
|
| 101 | Expedition 16 Crew |
2008.1.31 | 7H10M | EMU | · replacement of the failed Bearing Motor Roll Ring Module (BMRRM) of S4 truss · inspection of the starboard Solar Alpha Rotary Joint (SARJ) |
| 100 | 2007.12.18 | 6H56M | EMU | · inspection of the Beta Gimbal Assembly (BGA) · inspection of the starboard Solar Alpha Rotary Joint (SARJ) |
|
| 99 | 2007.11.24 | 7H04M | EMU | · outfitted the Harmony · inspection of the starboard Solar Alpha Rotary Joint (SARJ) |
|
| 98 | 2007.11.20 | 7H16M | EMU | · outfitted the Harmony | |
| 97 | 2007.11.9 | 6H55M | EMU | · preparation for the relocation of Pressurized Mating Adapter 2 (PMA-2) | |
| 96 | STS-120 (10A) | 2007.11.3 | 7H19M | EMU | · repair of Solar Array Wing (SAW) on P6 truss |
| 95 | 2007.10.30 | 7H08M | EMU | · installation of P6 truss · installation of Main Bus Switching Unit (MBSU) on External Stowage Platform 2 (ESP-2) · inspection of the port Solar Alpha Rotary Joint (SARJ) |
|
| 94 | 2007.10.28 | 6H33M | EMU | · preparation for the relocation of P6 truss · inspection of the starboard Solar Alpha Rotary Joint (SARJ) · outfitted the Harmony |
|
| 93 | 2007.10.26 | 6H14M | EMU | · retrieval S-Band Antenna Structural Assembly · preparation for removal of harmony · preparation for the relocation of P6 truss |
|
| 92 | STS-118 (13A.1) | 2007.8.18 | 5H02M | EMU | · installation of the External Wireless Instrumentation System (EWIS) antenna · installation of a stand for the Orbiter Boom Sensor System (OBSS) · retrieval MISSE-3,-4 (Material ISS Experiment-3,-4) |
| 91 | 2007.8.15 | 5H28M | EMU | · upgrade of S-band communication system · relocation of CETA (Crew and Equipment Translation Aid) carts |
|
| 90 | 2007.8.13 | 6H28M | EMU | · replacement of Control Moment Gyroscopes (CMG) | |
| 89 | 2007.8.11 | 6H17M | EMU | · installation of S5 truss · retraction of the forward heat-rejecting radiator of Early External Active Thermal Control System (EEATCS) on the P6 truss |
|
| 88 | Expedition 15 Crew |
2007.7.23 | 7H41M | EMU | · jettison of the Early Ammonia Servicer (EAS) · installation of a Video Stanchion Support Assembly (VSSA) · reconfiguration of a power supply for an S-Band Antenna Assembly |
| 87 | STS-117 (13A) | 2007.6.17 | 6H29M | EMU | · preparation for activation of the SARJ (Solar Alpha Rotary Joint) · removal a hardware from S3 truss · installation of a LAN cable |
| 86 | 2007.6.15 | 7H58M | EMU | · repair of a protruding thermal blanket on orbital maneuvering system (OMS) pod · installation of the hydrogen vent valve of a oxygen generation system (OGS) · retraction of the starboard SAW (Solar Array Wing) on P6 trusss |
|
| 85 | 2007.6.13 | 7H16M | EMU | · retraction of the starboard SAW (Solar Array Wing) on P6 truss · preparation for activation of the SARJ (Solar Alpha Rotary Joint) |
|
| 84 | 2007.6.11 | 6H15M | EMU | · installation of S3/S4 truss · preparation for deployment of SAW (Solar Array Wing) on S4 truss |
|
| 83 | Expedition 15 Crew |
2007.6.6 | 5H37M | Orlan | · installation of Biorisk on Pirs · installation of Ethernet cable on the exterior of Zarya · installation of Service Module Debris Protection (SMDP) panels |
| 82 | 2007.5.30 | 5H25M | Orlan | · installation of Service Module Debris Protection (SMDP) panels · rerouting a cable for a Global Positioning System antenna to be used with the ATV |
|
| 81 | Expedition 14 Crew |
2007.2.22 | 6H18M | Orlan | · retraction the antennas for the Kurs automated rendezvous system · inspection of navigation antenna to be used for docking of the ATV · inspection of the German robot arm |
| 80 | 2007.2.8 | 6H40M | EMU | · removing and jettisoning thermal shrouds · deployment Unpressurized Cargo Carrier Assembly Attachment System (UCCAS) of the P3 truss |
|
| 79 | 2007.2.4 | 7H11M | EMU | · rerouting lines of cooling system · retraction of the aft heat-rejecting radiator of Early External Active Thermal Control System (EEATCS) on the P6 truss · disconnection and stowing fluid line attached to the Early Ammonia Servicer (EAS) |
|
| 78 | 2007.1.31 | 7H55M | EMU | · rerouting lines of cooling system · retraction of the starboard heat-rejecting radiator of Early External Active Thermal Control System (EEATCS) on the P6 truss · disconnection and stowing fluid line attached to the Early Ammonia Servicer (EAS) |
|
| 77 | STS-116 (12A.1) | 2006.12.18 | 6H38M | EMU | · retraction of the port SAW (Solar Array Wing) on P6 truss |
| 76 | 2006.12.16 | 7H31M | EMU | · reconfiguration of power system · installation of AGB (Adjustable Grapple Bar) · stowed SMDP (Service Module Debris Panel) · retraction of the port SAW (Solar Array Wing) on P6 truss |
|
| 75 | 2006.12.14 | 5H00M | EMU | · reconfigured power system · relocated CETA (Crew and Equipment Translation Aid) carts |
|
| 74 | 2006.12.12 | 6H36M | EMU | · installation of P5 truss · exchanged ETVCG (External TV Camera Group) |
|
| 73 | Expedition 14 Crew |
2006.11.22 | 5H38M | Orlan | · tried to stow the antennas for the Kurs automated rendezvous system · moved a navigation antenna to be used for docking of the ATV · installed BTN-Neutron |
| 72 | STS-115 (12A) | 2006.9.15 | 6H42M | EMU | · retrieved MISSE 5 (Materials International Space Station Experiment 5) · fixed a P6 BGA (Beta Gimbal Assembly) · prepared radiator of PVTCS (Photovoltaic Thermal Control System) for deployment · exchanged S-Band radio antenna |
| 71 | 2006.9.13 | 7H11M | EMU | ·installation of P3/P4 truss | |
| 70 | 2006.9.12 | 6H26M | EMU | ·installation of P3/P4 truss | |
| 69 | Expedition 13 Crew |
2006.8.3 | 5H54M | EMU | · installed FPMU (Floating Potential Measurement Unit) and MISSE (Materials on International Space Station Experiment) · exchanged RJMC (Rotary Joint Motor Controller) · installed jumper and SPD (Spool Positioning Device) · test of an infrared camera |
| 68 | STS-121 (ULF1.1) |
2006.7.12 | 7H11M | EMU | · evaluation of repairing damage to RCC(Reinforced Carbon Carbon) · capability testing of infrared camera · remove FGB(fixed grapple bar) from pump module, and install FGB on ammonia tank |
| 67 | 2006.7.10 | 6H47M | EMU | · pump module installed · exchanged TUS(Trailing Umbilical System) Reel Assembly |
|
| 66 | 2006.7.8 | 7H31M | EMU | OBSS test as a work platform | |
| 65 | Expedition 13 Crew |
2006.6.1 | 6H31M | Orlan | · Electron vent repair · Kromka retrieval · Biorisk retrieval · Reposition a cable for a navigation antenna to be used for docking of the ATV · Contamination Monitoring Unit retrieval · exchanged camera on the MBS |
| 64 | Expedition 12 Crew |
2006.2.1 | 5H43M | Orlan | · SuitSat
release · a cable-cutting device maintenance · Biorisk retrieval |
| 63 | 2005.11.7 | 5H22M | EMU | · New video camera installed · Probe removal |
|
| 62 | Expedition 11 Crew |
2005.8.18 | 4H58M | Orlan | · Biorisk retrieval · MPAC&SEED / Matroshka removal · exchanged sample in the SKK |
| 61 | STS-114 (LF1) |
2005.8.3 | 6H 1M | EMU | Noguchi Soichi ESP-2 / FRGF / MISSE / gap fillers |
| 60 | 2005.8.1 | 7H14M | EMU | Noguchi Soichi CMG-1 |
|
| 59 | 2005.7.30 | 6H50M | EMU | Noguchi Soichi CMG-2 / ESPAD / MISSIE |
|
| 58 | Expedition 10 Crew |
2005.3.28 | 4H30M | Orlan | · ATV navigation antennas
installation · the large “Lira” antenna inspection · a small Russian technology satellite deployment |
| 57 | 2005.1.26 | 5H28M | Orlan | · a prototype German robot arm installation · Russian biomedical experiment |
|
| 56 | Expedition 9 Crew |
2004.9.3 | 5H21M | Orlan | ATV navigation antennas installation |
| 55 | 2004.8.3 | 4H30M | Orlan | ATV navigation antennas and Laser reflectors installation | |
| 54 | 2004.6.30 | 5H40M | Orlan | ||
| 53 | 2004.6.24 | 14M | Orlan | ||
| 52 | Expedition 8 Crew |
2004.2.26 | 3H56M | Orlan | |
| 51 | Expedition 6 Crew |
2003.4.8 | 6H26M | EMU | |
| 50 | 2003.1.15 | 6H51M | EMU | Unfurl P1 truss radiator |
|
| 49 | STS-113 (11A) |
2002.11.30 | 7H 0M | EMU | P1 Truss |
| 48 | 2002.11.28 | 6H10M | EMU | ||
| 47 | 2002.11.26 | 6H45M | EMU | ||
| 46 | STS-112 (9A) |
2002.10.14 | 6H36M | EMU | S1 Truss |
| 45 | 2002.10.12 | 6H 4M | EMU | ||
| 44 | 2002.10.10 | 7H 1M | EMU | ||
| 43 | Expedition 5 Crew |
2002. 8.23 | 5H21M | Orlan | |
| 42 | 2002. 8.16 | 4H25M | Orlan | ||
| 41 | STS-111 (UF2) |
2002. 6.13 | 7H17M | EMU | Crew rotation, MPLM |
| 40 | 2002. 6.11 | 5H 0M | EMU | ||
| 39 | 2002. 6. 9 | 7H14M | EMU | ||
| 38 | STS-110 (8A) |
2002. 4.16 | 6H37M | EMU | S0 Truss |
| 37 | 2002 .4.14 | 6H27M | EMU | ||
| 36 | 2002. 4.13 | 7H30M | EMU | ||
| 35 | 2002. 4.11 | 7H48M | EMU | ||
| 34 | Expedition 4 Crew |
2002. 2.20 | 5H47M | EMU | |
| 33 | 2002. 1.25 | 5H59M | Orlan | ||
| 32 | 2002. 1.14 | 6H3M | Orlan | ||
| 31 | STS-108 (UF-1) |
2001.12.10 | 4H12M | EMU | Crew rotation, MPLM |
| 30 | Expedition 3 Crew |
2001.12. 3 | 2H46M | Orlan | |
| 29 | 2001.11.12 | 5H04M | Orlan | ||
| 28 | 2001.10.15 | 5H52M | Orlan | ||
| 27 | 2001.10. 8 | 4H58M | Orlan | ||
| 26 | STS-105 (7A.1) |
2001. 8.18 | 5H29M | EMU | Crew rotation, MPLM |
| 25 | 2001. 8.16 | 6H16M | EMU | ||
| 24 | STS-104 (7A) |
2001. 7.20 | 4H 2M | EMU | Airlock |
| 23 | 2001. 7.17 | 6H29M | EMU | ||
| 22 | 2001. 7.14 | 5H59M | EMU | ||
| 21 | Expedition 2 Crew |
2001. 6. 8 | 19M | Orlan | |
| 20 | STS-100 (6A) |
2001. 4.24 | 7H40M | EMU | SSRMS |
| 19 | 2001. 4.22 | 7H10M | EMU | ||
| 18 | STS-102 (5A.1) |
2001. 3.13 | 6H21M | EMU | Crew rotation, MPLM |
| 17 | 2001. 3.11 | 8H56M | EMU | ||
| 16 | STS-98 (5A) |
2001. 2.14 | 5H25M | EMU | Destiny |
| 15 | 2001. 2.12 | 6H50M | EMU | ||
| 14 | 2001. 2.10 | 7H34M | EMU | ||
| 13 | STS-97 (4A) |
2000.12. 7 | 5H10M | EMU | P6 Truss |
| 12 | 2000.12. 5 | 6H37M | EMU | ||
| 11 | 2000.12. 4 | 7H33M | EMU | ||
| 10 | STS-92 (3A) |
2000.10.18 | 6H56M | EMU | Z1 truss and the PMA-3 |
| 9 | 2000.10.17 | 6H48M | EMU | ||
| 8 | 2000.10.16 | 7H 7M | EMU | ||
| 7 | 2000.10.15 | 6H28M | EMU | ||
| 6 | STS-106 (2A.2b) |
2000. 9.11 | 6H14M | EMU | Logistics and supply mission for the ISS |
| 5 | STS-101 (2A.2a) |
2000. 5.21 | 6H44M | EMU | Repair of Zarya and supply mission |
| 4 | STS-96 (2A.1) |
1999. 5.29 | 7H55M | EMU | Logistics and supply mission for the ISS |
| 3 | STS-88 (2A) |
1998.12.12 | 6H59M | EMU | FGB-NODE-1 Docking |
| 2 | 1998.12. 9 | 7H 2M | EMU | ||
| 1 | 1998.12. 7 | 7H21M | EMU | ||
|